BUILDING THE FUTURE TOGETHER

Structural Condition Assessment of Hangar 110 at Archerfield Airport

Project Structural Condition Assessment of Hangar 110 at Archerfield Airport
Client Archerfield Airport Corporation
Project Value < $100k
Project Overview The World War II era Bellman Hangar at Archerfield Airport was damaged during a severe storm. The cause of this damage was identified as internal pressures causing the structure to lift and fall back down. The client required a structural assessment of the hangar to determine its integrity.
JJR Involvement The project involved the following:

  • Visual structural inspection of the hangar;
  • Review and analysis of the structural integrity of the hangar;
  • Develop proposed remediation works to repair the hangar;
  • Contract administration; and
  • Project management of the confirmed works.