Client Archerfield Airport Corporation
Project Value < $100k
Project Overview Archerfield Airport were investigating upgrading the northern apron tie-down area through pavement sealing works. An options analysis and reverse brief were required for the project.
JJR Involvement The project involved the following tasks:

  • Cost estimate for northern apron pavement works;
  • Reviewing and analysing cost estimate for northern apron tie-down area; and
  • Cost estimate for northern apron overlay.

A final report detailing the options for upgrading the tie-down area including cost breakdowns was produced to the client.