JJR were requested by the Council to conduct review and assessment of the current design for the civil and structural components including:
Structural design of the posts and sleepers
Geotechnical stability of the spectator stands
Local drainage and grading design (based on rough levels only)
JJR Involvement :
JJR required scope of work were defined as:
Conduct site inspection
Inspection of the structure including posts, sleepers and record any issues
Take measurements of the overall layout and each structural component
Inspection of the drainage system. (i.e. overland flow paths etc.)
Take photographs as required
Conduct site survey
Engage surveyor and liaise
Conduct site surveying and prepare survey drawing
Conduct civil and structural assessment
Structural assessment of the existing spectator structures and redesign, if required
Design of civil works including drainage and local grading
Prepare structural drawing package (upgraded if required) and specifications
Prepare civil drawings package
Prepare assessment and recommendations report
Project cost estimate
Prepare cost estimate for structural works (upgraded works or redesign)
Prepare cost estimate for civil works