Leichardt Market Place and Connection Points for Structures
Project :
Leichardt Market Place and Connection Points for Structures
Client :
PowerPark Systems
Project Value :
Project Overview :

Engineering designs and drafting was undertaken for PowerPark’s Leichardt Market Place project. The project involved the installation of six arrays onto a concrete slab with post-tensioned cables.

JJR Involvement :

The scope of works for this project included providing structural engineering services for structures 1 to 6 as outlined below:

  • Structure 1 – A column that sat on a beam with the beam finishing approximately 1,100mm from the wall. A single cantilever structure column sat 1,500mm inside the wall, meaning it was not supported by the beam;
  • Structures 2, 3 and 4 were Position base plates centred over current post-tensioned cable locations, approximately 750mm from the wall;
  • Structure 5 – The existing column was located off the beam with the beam being to one side of the centre line of the car park; and
  • Structure 6 – The existing column was located off the beam completely with no beam near the structure.
Scroll to Top
Civil Engineering Consultant

Get Quote

Welcome to JJ Ryan Consulting! Thank you for your interest in our services. Please fill out the form, and our designated contact person will reach out to you shortly.